Pile caps can be designed either by the truss analogy or by bending theory (see BS 8110: Part 1: 3.11.4.1(5)). In this example bending theory will be used.
For a pile cap with closely spaced piles, in addition to bending and bond stress checks, a check should be made on the local shear stress at the face of the column, and a beam shear check for shear across the width of the pile cap. For more widely spaced piles (spacing > 3 × diameter), a punching shear check should also be carried out.
Local shear check
The ultimate column load is Pu = 6400 kN.
Length of column perimeter is u = 2(400 + 400) = 1600 mm.
The shear stress at the face of the column is
Bending shear check
In accordance with BS 8110: Part 1: 3.11.4.3, shear is checked across a section 20% of the diameter of the pile (i.e. D/5) inside the face of the pile. This is section A–A in Fig. 14.30.
The shear force across this section – ignoring the self-weight of the pile cap, which is small in comparison – is given by
The corresponding shear stress is given by vu = Vu/bvd, where bv is the breadth of section for reinforcement design.
In accordance with BS 8110: Part 1: 3.11.4.4, this must not exceed (2d/av)vc where av is defined in Fig. 14.30 and vc is the design concrete shear stress from BS 8110: Part 1: Table 3.8. Thus
For grade C35 concrete, from BS 8110: Part 1: Table 3.8, assuming six T25 bars, the minimum value of vc is 0.4 N/mm2, giving
Thus, provided the average effective depth exceeds d = 846 mm (the local shear check), minimum reinforcement to satisfy bond and bending tension requirements will be adequate in this instance.
The necessary depth for the pile cap is
h = d + 25(diameter bar) + 75(cover)
= 846 + 100
= 946 mm ⇒use h = 950 mm
Fig. 14.30 Pile cap design example. |
waw complicated calculations also about pilling
ReplyDeleteNeeded this, Thanks!
ReplyDeleteMay i ask? Shouldn't the ult column load divided by 4 instead of 2 in the shear force calculation since the column load will be transferred to all four piles?
ReplyDeletehow you got av please describe inn details
ReplyDeleteGood day. I have a question. By referring to Figure 14.30, how do you find the av? I appreciate if you could answer my question. Thank you :)
ReplyDeleteHi - In this example av is calculated as below:
ReplyDeleteav = (900 - 400)/2 + (600/5) = 370mm
However, this sketch appears to be wrong as minimum spacing between piles should be 3* Pile Dia. = 3*600 = 1800mm
If that was the case then av can be calculated as:
av = (2*Pile Dia. - Column width)/2 + (Pile Dia/5)
Min pile spacing should be 2.5*dia and in this case it's 2.5*600 = 1500, which is correct
ReplyDeleteWhere is it written that punching shear should only be checked if pile spacing is greater than 3x diameter?
ReplyDelete